When the frame does not match the engineering: Truganina frame findings
Beams at the wrong size, connections fixed another way and strongbacks without grips. Why frame stage on a Truganina build is a drawings exercise.
Practical completion is when the builder says the house is finished. The PCI checks that claim room by room and up on the roof before you accept the keys.
One of our inspectors will call you back. If it is urgent, call 1300 471 805.
Across our Truganina handovers the roof produces the most serious findings: cracked tiles, flashings left unsealed against the cladding, penetrations without proper flashing, cappings screwed through the top. Inside, leaking showers and upstairs bedroom windows without the 125mm opening limit are the items that matter most.



Annotated findings from Pre-handover (PCI) inspections.





1Bored piersWith the holes drilled and cages placed, before the concrete truck is booked
2Slab pre-pourSteel tied, pods down, plumbing in, and the pour still a day or two away
3FrameRoof trusses on, frame complete, and nothing wrapped or clad yet
4Lock-up (pre-plaster)Bricks laid, windows fitted, roof on, and the plasterboard not yet delivered
5FixingPlaster up, doors hung, cabinets in, painters not yet started
6WaterproofingMembrane cured in every wet area, tiles still in their boxes
Beams at the wrong size, connections fixed another way and strongbacks without grips. Why frame stage on a Truganina build is a drawings exercise.

Shower set-downs under the wall line, slab edges in the cavity and honeycombed concrete. What we measure when the frame first sits on the slab.

Why the lock-up visit on a Truganina build rechecks the frame report, and what a cut top plate, slack bracing and missing tie-downs have in common.
Instant online pricing, or talk to the booking team on 1300 471 805.
Practical completion inspection. It is the independent check before handover, sometimes called a pre-handover inspection.
Two to three hours for a typical single storey Truganina home, longer for a double storey with a full roof check.
Yes, where safe access is possible. Many of the most serious handover findings in Truganina are on the roof.
Your contract and drawings, the NCC and the Guide to Standards and Tolerances 2015.
Yes, and we recommend it. We walk you through the main items at the end.
Send the report to your builder and agree a date for the items to be fixed. We can reinspect before you take possession.